From 1 April 2027 everyone on a site of €500,000 or more registers arrival and departure personally. Which sites, who, which phone, what to prepare.
On this page
From 1 April 2027, on every site where the works total €500,000 or more excluding VAT, each person who works there registers an IN when arriving and an OUT when leaving, personally, on the site and at that moment. The employer or the office can no longer register the crew in advance, and the current Checkinatwork service, which accepts one registration per day, stops being available for this kind of work on that date. The rule comes from the programme law of 30 May 2026 and the service is called Check in and out at work (CIaO).
Last checked on 8 November 2026. This is general information and no substitute for legal advice, and your social secretariat or your accountant can confirm how it applies to your own sites.
What changes on 1 April 2027
The RSZ (ONSS in French, the federal social security office) announced the date in a notice of 30 July 2026: the obligation to register IN and OUT is extended to works in immovable property, except cleaning, and to the delivery of concrete ready for pouring, on sites where the total amount excluding VAT is €500,000 or more. The legal basis is the programme law of 30 May 2026, title 6, chapter 1, articles 124 to 131, which leaves the start date to a royal decree, at the latest 1 January 2027. The Royal Decree of 16 September 2026, published in the Belgian Official Gazette on 25 September 2026, names 1 January 2027, but the RSZ has announced that the obligation will only apply from 1 April 2027, to give firms time to prepare, and that Checkinatwork stays available for these works until then. This article follows the RSZ's date.
| Checkinatwork, until 31 March 2027 | Check in and out at work, from 1 April 2027 | |
|---|---|---|
| What is registered | Presence, once a day | An IN on each arrival and an OUT on each departure |
| When | Before the person starts work | Immediately and on the site |
| Who may do it | The employer or contractor, or the worker himself | Only the person who works |
| In advance | Possible | Not possible |
| Breaks | Not registered | Not registered in construction |
The two columns come from the RSZ pages on Checkinatwork and on Check in and out at work. Registration of presence on large sites is not new: it has existed since 1 April 2014, first above €800,000 and, for works started after 29 February 2016, above €500,000 (RSZ, works in immovable property). What changes is who presses and when.
Which sites fall under it
A site falls under the rule when the total amount of the works is €500,000 or more excluding VAT, and the RSZ counts the sum of the main contracts on the same declaration of works (aangifte van werken, déclaration de travaux), not the size of your own contract (RSZ CIaO FAQ, question 6). The obligation starts as soon as that amount is reached, either at the start or during the works, and it ends at provisional acceptance, for which the official report is the proof; warranty works after final acceptance are no longer covered (RSZ, works in immovable property). Because registration hangs on the declaration of works, a site without a declaration number cannot be registered at all.
Take two sites to see the method. A general contractor in Hasselt builds six flats; the declaration of works holds three main contracts, €340,000 for the shell, €120,000 for the roof and €140,000 for the technical installations, which makes €600,000. That site is in scope from the first day, for everyone on it, including the plasterer who works for the roofer as an independent subcontractor and the safety coordinator who comes once a week. The roofer's own contract of €120,000 does not matter, because the sum on the declaration decides. A renovation firm in Mechelen, on the other hand, renovates a house for €300,000 with two subcontractors and no other main contract on the declaration; it still files a declaration of works, but the site is below €500,000 and nobody has to check in. If an extension to that contract later takes the total to €510,000, registration starts from the moment the amount is reached.
Who has to check in and out
Every natural person who works on the site registers himself. The RSZ names employees, temporary agency workers, students and interns, but also independents (zelfstandigen, indépendants) and their helpers, including a subcontractor who works alone, and the site management, such as the architect or the engineering office that supervises the works (RSZ, works in immovable property). The law adds the safety coordinator and treats the contractor who files the declaration of works as the site management in charge of execution (Welfare at Work Act, article 31bis).
Each registration contains the identity of the person, the enterprise number of the employer (or of the independent, for someone who works for himself), the time of each arrival and departure and the number of the declaration of works (Welfare at Work Act, article 31ter; the explanatory memorandum, Chamber document 56 1378/001, says the same). The time that counts is the moment the RSZ records the data in its database, which it timestamps on receipt, and registering in advance is not allowed (Royal Decree of 16 September 2026, articles 4 and 5).
Why the office can no longer register the crew
Today a planner can register the whole crew for tomorrow from the office. That ends because the legislator wanted the registration to show who is really on the site at what time. The explanatory memorandum (56 1378/001, pages 91 to 94) says (my translation from the Dutch) that the registration “can no longer be done in advance by the employer in the place of the employee” and that the employee himself is responsible for registering his presence. The same text protects the employer that has done its part: once it has taken the measures needed so that each person can register, it is not responsible for the forgetfulness, mistakes or refusal of the worker. Responsibility is shared between the contractor who puts someone to work and the person who does the work, as the RSZ page puts it.
Do your workers need a smartphone
The law does not require you to hand out smartphones. The explanatory memorandum says it in so many words: “it is not provided that the employer must give its employees a smartphone”, and it describes the system as neutral about technology, so a badge or a QR code can work as long as the registration reaches the RSZ. What you must do is make registration possible for every person you put to work.
The RSZ has not published a construction FAQ on this yet, but its FAQ for the cleaning sector, where CIaO has applied since 2024, shows how it reads the same principle. The contractor chooses the means of registration; if workers use their own phone, that should be agreed in the work rules or the employment contract; and if a worker does not agree to use his own phone, the employer has to provide another means, such as a company phone (questions 20 and 55). In cleaning, a collective agreement gives €7 to a worker who uses his own smartphone. I found no such allowance for construction (joint committee 124) on 8 November 2026, so treat that as an open point to ask your social secretariat about.
No signal, a flat battery or a service down
The cleaning FAQ (questions 57 to 59) treats outages that nobody controls, such as an internet provider or power failure, an itsme outage or a failure of the RSZ's own service, as force majeure. Keeping proof of the outage is in your own interest, although you do not have to send it to the RSZ. A faulty system installed by a software company is different: the contractor stays responsible for the registration system working, even when a supplier built it (question 56). A forgotten phone or a flat battery is not force majeure either: according to the RSZ's procedures for technical failure, negligence and mistakes, no registration can be made in that case and the person risks a sanction if there is an inspection. A registration made with a mistake, such as a wrong declaration number, is reported to the RSZ through its web form within 30 days.
For software that connects through the RSZ's REST service, the RSZ's technical manual adds a rule that shapes daily practice. A registration that reaches the RSZ more than ten minutes after it was made is refused, and the sender cannot cancel a registration, only ask the RSZ to correct it. The rule comes from the developer documentation, not from the law, but it fits the royal decree's timestamp rule described above. It explains why a press made in a cellar without signal at 7:02 and sent at 7:40 will not count.
Foreign and posted workers
For a Romanian SRL posting five workers to a site in Antwerp, three things come before the first IN. The employer makes a Limosa declaration before the work starts and gives each worker the L1 proof. The Belgian client or contractor who uses them should ask for that proof, because a client or contractor that does not report a missing L1 proof can itself be prosecuted. Independents working in construction declare too, and the exemption for short assembly work does not apply to construction. Each worker then needs an identification number that CIaO accepts: the RSZ's FAQ (question 19) names the national number (INSZ, NISS) or a BIS number, with the employer identified by its Belgian enterprise number or, for a foreign company, its own identification number. Today's Checkinatwork accepts the L1 number or a scan of the Limosa QR code; whether CIaO will accept a Limosa number without a BIS number was not settled on 8 November 2026, so the safe course is to request BIS numbers now.
The third point is practical, and the High Council for Prevention and Protection at Work raised it itself in its advice no. 281 of 2 June 2026: foreign workers find it hard to register on site when no registration device is present there, because it is currently not technically possible for them to use the mobile application. A worker without a Belgian eID or itsme therefore needs a means that does not depend on Belgian identity apps, such as an employer's system that sends through the employer's own connection to the RSZ while the worker still presses himself. The FPS Employment points to information on Checkinatwork in Dutch, French and German, but not in Romanian, so a single page of instructions in Romanian for your own crew is time well spent.
Who is liable, and what is still unclear
Liability runs along the whole chain. The registration system is passed down from the site management to every contractor and subcontractor, and each of them shares responsibility for delivering, installing and keeping the registration device on the site in working order (Welfare at Work Act, article 31quater). Each contractor and subcontractor also has to make sure that registrations are sent correctly and immediately, take measures so that its own subcontractors register, and take measures so that every person who enters the site on its behalf can register on arrival and on departure (article 31quinquies). The employer provides the means of registration, and when that means is the RSZ's online application, every person needs a means of his own (article 31sexies).
The explanatory memorandum says the sanctions stay “unchanged” (56 1378/001, pages 92 and 93), and the Social Penal Code sets them. Site management, a contractor or a subcontractor that breaches these duties commits a level 3 offence, which becomes level 4 when the breach caused damage to health or a work accident (article 132). Since 1 September 2026, level 3 means, among other penalties, a criminal fine of €1,600 to €16,000 or an administrative fine of €800 to €8,000, and level 4 a criminal fine of €4,800 to €56,000 or prison of six months to three years, or an administrative fine of €2,400 to €28,000 (article 101). The fine is multiplied by the number of persons concerned, up to a hundred times the maximum (article 103), and the surcharge decimes of article 102 come on top. The person who does not register his own arrivals and departures commits a level 1 offence (article 132/1), which means an administrative fine of €80 to €800.
One point was still open on that date: the royal decree names 1 January 2027 and the RSZ 1 April 2027, and I found no text that says how the three months in between will be treated, so ask your social secretariat how it handles them. The RSZ says more information will follow on its portal, so it is worth checking the CIaO page again in February 2027.
The checklist
This is one list in the order I would work through it, with the moment each step belongs to.
- Before the end of 2026, list your sites whose declaration of works totals €500,000 or more excluding VAT and that will still run after 1 April 2027, counting all main contracts on the same declaration.
- Check that each of those sites has a correct declaration of works, because every IN and OUT refers to its number.
- Make sure your company has a main access manager on the social security portal, who can sign in with eID or itsme and create the accesses your tools need.
- Collect the national number or BIS number of every person who will work on those sites, and for posted workers check the Limosa L1 and request BIS numbers where they are missing.
- Decide per person how he will register (own phone with a written agreement, company phone, or a badge or terminal that sends to the RSZ), and plan a company phone for anyone who refuses to use his own.
- Ask your subcontractors in writing how their people will register, since you share responsibility for the registration system on your site.
- If you use software for it, set up its connection in January and test it against the RSZ's simulation environment, never against production with invented hours.
- In February, inform your workers in writing that they register IN on arrival and OUT on leaving, themselves and on site, and update the work rules for the use of phones.
- In March, rehearse a day without signal with one crew and agree who keeps the proof and who asks the RSZ for corrections.
- From 1 April 2027, have the site manager check each day who is in, who is missing and what the RSZ remarked, and ask for corrections within 30 days.
What to do next
If none of your sites reaches €500,000 on its declaration of works, nothing changes for you in April, apart from checking each new contract as it comes in. This week, two things cost nothing: open your declarations of works and add up the main contracts per site, and ask your social secretariat whether a phone allowance will apply in construction. If your crew includes posted workers, start the BIS number requests now, because they take longer than a phone setup. The daily side, what a worker actually does on the phone, is described in what the crew really does on the phone.
In Beloplan, each worker checks in and out himself from the phone app on the site, and the registration goes to the RSZ's Check in and out at work service. The connection has been available in production since 5 November 2026. Each company starts on the RSZ's simulation and sends real registrations only after its administrator creates a production credential in the settings, so you can test with your own crew well before 1 April 2027. Each worker can enter his own national or BIS number in the app, Beloplan refuses a check-in without one, and the office sees who has not entered it yet and can send them a reminder. The reminder only asks; it never checks anyone in.
The other rule changes of the same years are covered in Peppol for Belgian contractors and, for the withholding when you pay a subcontractor on the same declaration of works, in VAT on building work.
Sources
All checked on 8 November 2026.
- RSZ, Check in and out at work (notices of 30 July and 23 October 2026), Checkinatwork, works in immovable property and procedures for technical failure, negligence and mistakes, in Dutch, since the RSZ publishes no English version.
- RSZ, FAQ on Check in and out at work, cleaning sector, version of 15 October 2025, used by analogy.
- Programme law of 30 May 2026, title 6, chapter 1, articles 124 to 131, and Royal Decree of 16 September 2026, Belgian Official Gazette of 25 September 2026.
- Welfare at Work Act of 4 August 1996, articles 31bis to 31septies, and Social Penal Code, articles 101 to 103, 132 and 132/1, consolidated versions on Justel.
- Chamber of Representatives, draft programme law, document 56 1378/001, 23 February 2026, explanatory memorandum.
- High Council for Prevention and Protection at Work, advice no. 281, 2 June 2026.
- Limosa and FPS Employment, formalities for construction works.
Did this help?